Gauteng rail corridors “future-proofed” as Siemens Mobility completes massive Germiston resignalling project: Siemens-20220210-03417

12 Apr 2022

Gauteng rail corridors “future-proofed” as Siemens Mobility completes massive Germiston resignalling project

  • Siemens Mobility South Africa completes three year re-signalling project at vital Germiston station
  • Increased volume of trains now able to pass through Germiston station supporting efficient passenger journey times
  • Siemens Mobility investment in interlocking testing facility helps reduce testing time both in the factory and on site by almost 50%

Siemens Mobility South Africa has completed a massive three-year project to resignal the busy and vital railway junction at Germiston, Gauteng.

The project, part of the Gauteng Resignalling Programme currently being delivered by Siemens Mobility South Africa on behalf of the Passenger Rail Agency of South Africa (PRASA), involved a complete resignalling of Germiston station, one of the busiest railway junctions in Africa.

The complex has 10 platforms and 23 connecting lines and lies at the heart of PRASA’s Gauteng network.

All trains travelling between east and west and north and south run through Germiston, making this a very complex station to work on, said Thomas Mashishi, project execution manager at Siemens Mobility.

“In addition, Transnet Freight Rail (TFR) also uses this section, moving from India and Elsburg stations, which we had to interface with as part of the Germiston execution of works,” he said.

The station also has several yards, sidings and staging lines for freight services. 

The project saw Siemens Mobility install seven equipment rooms, 57 cable junction boxes and 579 trackside elements.  Elements are trackside components such as track vacancy detection systems that detect train position, points and switches that allow trains to change direction and signals that communicate to the driver. 

All elements are connected to computers and logic controllers with cabling buried in more than 23km of trenches within the complex.

The station complex originally had 726 elements. Restructuring the station, however, allowed that number to be reduced to 580 elements which in turn provides 500 routes.

“The restructuring gives the train control officers greater flexibility, allowing PRASA to increase volumes through the station,” said Siemens Gauteng Signalling project manager Lucio Lefebvre.

The project also involved changes to the track layout with 180 turnouts being replaced while new overhead traction equipment (OHTE) and gantries were added.

So far, the resignalling project has comprised two five-year contracts spread across 86 stations, has taken 7.5 million working hours and followed a schedule of 12,000 line items.

The Germiston station complex, the last of the project’s mega stations to be completed, was handed over to PRASA in February 2022.

Due to the size and complexity of the station, testing and commissioning took much longer than the smaller stations with two test teams being used to facilitate testing the entire Germiston complex.

“Traditionally our two test teams work independently but for Germiston we had to bring in both test teams to ensure that we could cover the extensive testing that needed to be done,” said Mashishi.

The station is currently controlled from the new satellite Centralised Traffic Control (CTC) built by Siemens Mobility and situated at the Germiston PRASA building. The satellite complex has three new operating control desks, two of which control the station and one covering the section from Elsburg to Kwesine. 

These desks along with those on other Gauteng CTCs are to be transferred to the Gauteng Nerve Centre after which the satellite control centre will be used as a fallback option. In the case of a catastrophic failure at the Gauteng Nerve Centre (GNC), PRASA would be able to continue train operations seamlessly using the satellite CTC.

In a positive step for supporting South African industry, Siemens Mobility has also achieved more than 60% in terms of local content for the entire PRASA Gauteng resignalling programme.

“It is not just local content for Germiston, but the project as a whole,” said  Mashishi.

“All of the engineering work that has been done for the Gauteng resignalling project has been done locally, by our experienced and highly skilled team.”  

The local content includes locally developed South African Train Control Operating System (SATCOS) software — a train management tool used by operators.— while Siemens Mobility’s investment in a state-of-the-art interlocking testing facility (ITF) which helps reduce time required for testing both in the factory and on site by almost 50%. 

“We have also developed locally the light units that we use in all of our signals, ensuring that they suit local conditions in South Africa,” Mashishi added.

Completion of the Germiston complex gives PRASA the building blocks to boost network and service levels of SA’s railways to world-class level. It offers flexibility for bidirectional signalling as well as the ability to run more trains especially during peak hours where train overloading has been a problem in the past.

Dependable signalling also provides commuters with safe, reliable and predictable railway service, said Lefebvre.

The technology used at Germiston and other stations comprises programmable logic controllers (PLCs) and element control computers (ECCs), which spread throughout the station and the various elements. 

“We use SICAS S7, which forms a basis for the interlocking and SATCOS for the VDU, or the man/machine interface,” he added.

The SICAS system has a life expectancy of more than 30 years.

“It’s future-proof in that it forms a good platform to add on ETCS — the European Train Control System — giving the operator the ability to remotely control trains,” said Lefebvre.

Contact information

About Siemens